Saverio did three test samples for possible finishes for the wall plaster top coat. The upper sample was rustic, the bottom very white and shiny and the middle somewhere in between. We went for the middle option.
The other big topic of discussion was windows and doors - what can be refurbished, what will be new, which will have shutters and mosquito screens, the type of glazing:
- the front door will be refurbished
- the street balcony doors will be recreated but re-cycling the ironmongery
- the valley window will be replaced
- the door to the terrace will be one big pane of toughened glass
- the bathroom door we are postponing to allow further cogitation
The underfloor heating pipework has been ordered and due to arrive from Germany. By the next visit it should be installed and the top layer of cement laid over it. Then the original, salvaged floor tiles will be relaid. That means the kitchen fitters can come and take definitive measurements; the kitchen lead time is now the critical path. Only three weeks to go to the next visit.
Full set of pictures on Flickr: http://www.flickr.com/photos/markmclellan/sets/72157633777780557/